The Eagle Road Culvert Rehabilitation Project - Kirtland, Ohio
February 2005 PROJECT #04-KRT-002
Lake County Storm Water Management Department The Eagle Road project consisted of lining 150 feet of 72 inch corrugated metal pipe with 66 inch Large Diameter RSC 160 pipe. This large diameter pipe was inserted in 3 sections with the length of the 66 inch pipe being 50 feet. These sections were internally welded together. Once the pipe is welded in place, you have a monolithic one-piece pipe system. After the installation of the pipe, the annular space is then grouted. The following job site photos tell the story of the
product's ability to rehabilitate difficult culvert rehabilitation.
|
View to top of site |
View down stream |
Eagle Road View |
1 Piece of 66" large diameter pipe 50 feet long
|
Pipe ready to install in culvert |
Pipe to be installed |
Preparing for pipe installation |
Interior of pipe |
Pipe ready to install |
Pipe ready to install |
Installing pipe |
Rotating Pipe - Pipe rotation needed to weld bottom of pipe that was in flow line of
water |
Welding band and grout tubes |
Non-supported pipe |
Pipe ready to go in CMP |
Welding inside of pipe |
Welding inside of pipe |
view of 66" large diameter pipe installed at bulkhead |
Discharge side pipe installed |
Pipe installed in existing CMP |
Discharge view |
Metal culvert interior |
We offer on-site visits and would be pleased to quote your relining requirements free of charge!
Send us an e-mail: dvandam@davandam.com
Call our toll free number: 888-818-0017
Fax us your request toll free: 877-882-6339
|